Game-changing consistency: AMRC unifies project governance across eight sections

Complex high value manufacturing catapult centre implements Power Framework PPM to drive quality processes.

Brand
Sector

Public sector

Location

Sheffield, United Kingdom

PRODUCTS

Power Framework PPM

Executive Summary

  • The University of Sheffield’s Advanced Manufacturing Research Centre (AMRC) needed a standardised view of projects across eight different organisational technology centres 
  • Named internally “Harbour”, the organisational Project Portfolio Management (PPM) platform built with Power Framework PPM has enabled the AMRC to standardise process and governance across project plans, risk registers, progress reporting and quality checklists 
  • The AMRC received special acknowledgement on their ‘game-changing’ standardisation during their latest external audit – and are managing to redeploy and upskill staff across sections in weeks rather than months 

Challenges

The AMRC is a UK not-for-profit high value manufacturing catapult centre (HVMC), providing resource, skills and research-based process and efficiency solutions for clients ranging from Blue Chip to SME commercial engineering and manufacturing organisations. Wholly owned by Sheffield University, the AMRC’s purpose is to bring leading-edge research to practical production lines, de-risking innovation, increasing turnover and generating profit.  

With large numbers of projects on the go at the same time, across a wide variety of manufacturing sectors including aerospace, construction and digital, the AMRC has complex requirements for PPM. 

Angus Williams, the AMRC’s Head of Project Management, has the challenging task of navigating the PMO requirements of eight different delivery teams, each serving a different sector of the manufacturing industry. 

“I genuinely think that AMRC has probably the most complex set of requirements for Project Management integrations of any organisation I know,” says Angus. 

“We are multi-funded, through commercial contracts, network membership fees and subscriptions and various grant-based models. This poses a challenging business model to map to a single process.” 

“Add into the mix the fact that we are not-for-profit, and under justifiable scrutiny from external auditors on how we maximise effort for the funding we receive, the usual metrics for organisational Project Management success do not always apply.” 

Highlighting the specific problems that the AMRC were facing Angus says: “Prior to Harbour being developed, every part of the business was managing in different ways. It was proving impossible to understand the bigger picture of everything that was going on in the AMRC as a whole”. 

“It was also very difficult to move people around the business. With every section using their own methodology, the learning curve to transfer from one project environment to another was a challenge.”  

Solution 

Describing how AMRC came to work with Power Framework, Angus says: “We had been using Microsoft Project Server through a different company, but we weren’t very happy with that solution. So, we decided to go back to Microsoft and find a Project Management Gold Partner. 

“We were given a few references but as soon as we started talking to Power Framework they understood quite quickly where we were coming from. We engaged them in 2021 and they’ve been supporting us ever since.” 

The AMRC were looking for an end solution for project management, including utilising some CRM functionality to guard against customer data duplication and inconsistencies. 

“What we now have is internally called Harbour, an analogy which illustrates how our projects are conducted consistently within the virtual harbour walls, everything in one space including the PMO approach, financing, risk management, project planning, forecasting and lessons learned.” 

The solution has Power Framework PPM at the centre, utilising Microsoft Project plans for planning, costing, and resourcing; reporting through Power BI; document control and approvals through SharePoint and connected to Microsoft Dynamics CRM. 

“Fitting it all together and making it interact seamlessly is Power Framework’s speciality,” says Angus. 

Implementation Approach

Commenting on the approach to implementation Angus says: “We had a lot of requirements upfront, reflecting our dynamic and variable costing framework and critical success factors.” 

“About 70-80% of these requirements were addressed in Phase 1 of the implementation, providing our baseline system and a series of training courses upon launch.” 

At the time of writing in May 2024 Angus and his team are in Phase 2 of the implementation, addressing the remainder of Phase 1 requirements and additional ones that have emerged through adoption. 

“We’re continuing to tweak and develop as we’re living it,” Angus explains. “Short-term reporting, dashboard customisations and aligning our quality process questions with the system are on-going conversations.”

Adoption

“Power Framework have been influential in getting the senior leadership on board. Our CEO is always asking for information out of Harbour to back up business decisions, and this is key in driving adoption,” says Angus. 

“Meanwhile I’ve been nominating Superusers across each of the 8 groups, and they are training people in quick and efficient ways of using the platform. This is a trickle effect in terms of adoption, but with the senior sponsorship we have I know it’s going in the right direction and people will all come on board eventually.” 

Results

While Angus continues to mediate the PPM requirements of all the stakeholders, there are several stand-out achievements and lessons which ensure the AMRC will stay loyal to the platform. 

 

Quality Control Failsafe

“It’s not always easy to convey 30 years of project management experience to everyone, but Power Framework have helped us to align the system with our quality process,” Angus explains. 

“It’s designed to prompt the right person with the right question at the right time during a project, to make sure important tasks don’t get overlooked and failures are averted. 

“We have a representative working group in place to build trust in the quality process, and to make sure the system feeds the process and vice versa.”

Acknowledgement by external auditors

“At our last BSI external audit, we immediately received the feedback that Harbour has been a game changer for us in terms of consistency of information,” Angus says. 

“We are heads and shoulders above where we used to be and are expecting improvements year on year. So, this is a really good recognition that would not have been possible without Power Framework’s support.”

Greater resourcing agility and flexibility

“With Harbour, the learning curve of redeployed staff across different sectors has been reduced from six months to a couple of weeks!” exclaims Angus. 

“This is due to consistency in project process, information, and presentation of data. It has enabled a transformation in knowledge and capability across the entire organisation, and less tendency to be bogged down in silos.”  

 

Looking to the future

With such good progress under its belt the AMRC is set to continue maturing and refining their processes, as more teams from across the different sectors begin to use the platform.

“We will keep an eye on improving governance and good data quality,” says Angus, “as well as including functionality like automated timesheets and further enhancements to data dashboards.”

“We certainly see Power Framework as vital support going forward, whether in terms of fixing issues through their help desk, trouble shooting, or informing and developing our future use of the platform,” says Angus.

“They know what they’re doing, are a nice company to talk to and have a phenomenal work ethic.” 

 